T-Minus 14 Days And Counting

A 4D Approach to Construction Staging

3D Visualization turns into 4D Approach to Construction Staging Bridge in Boston, MA

Introduction

The North Washington Street Bridge on Route 99 is an important Boston arterial. It is the Easternmost bridge over the Charles River and provides local residents, commuters and bus riders with a vital connection between downtown Boston and Charlestown. It is also part of Boston’s famed FreedomTrail, connecting the North End neighborhood with other tourist destinations such as Bunker Hill and the U.S.S. Constitution.

Over more than a century of service, the bridge has been reconfigured and repaired multiple times to extend its lifespan. It currently costs the City of Boston between $3-5 million each year to keep it operational. Construction of a new “complete streets over water” bridge started in late 2018 and is expected to take up to 5 years to complete. Construction will include the erection of a temporary parallel bridge, and several stages involving rerouting of traffic on the bridge and at the intersections on each end.

Enter RDV Systems

Faced with the challenge of communicating a complex plan for maintenance of traffic, and with only two weeks before their first public meeting, contractor J.F. White turned to RDV Systems of Manchester, NH to provide a virtual model that shows not only the completed bridge, but all of the traffic routing configurations throughout the construction process. RDV came up with a very practical approach for developing a “4-D” model that shows the project changing over time.

“Traditional 4-D models usually show incremental steps of construction tied to a scheduling system and includes placement of equipment and materials. This is very laborious and quite expensive and in this case complete unnecessary. Given the short time frame and budget constraints, we focused on a single goal – communicating traffic flow changes during construction to the public.” Said Kevin Stewart, RDV’s Director of Operation for North America.

Bridge Layout – Stage 2 of 4

Intersection Layout – Stage 3 of 4

The RDV visualization technology includes assignment of model elements to layers, and the ability to use these layers to set up predefined View States. The resulting model included view states for the existing conditions, the final bridge and intersection configurations, and configurations at the four stages during construction where traffic flow patterns will change.

Bridge Construction Visualization | 4D Visualization | RDV Systems

Mission Accomplished

The initial 4-D model was delivered in two weeks for review by J.F. White and MassDOT at a cost that was well within their limited budget.The modeling of the surrounding existing conditions was facilitated by the availability of detailed Sketchup models of existing buildings from the Boston Planning and Development Agency’s website. As is often the case, seeing a 3D virtual model resulted in several significant improvements to the traffic maintenance plan which were quickly incorporated into the final product.

From the initial contact with RDV to the completed project RDV always quickly responded to the changes requested by JF White during the building of the model. RDV also assembled several video versions to be used during the public meetings. With the short duration that JF White had to assemble the videos, RDV met all of the task deadlines and JF White will definitely use RDV in the future.
Robert Nies, Project Manager, JF White Contracting, a Dragados Subsidiary

Virtual Tour

Scan the QR code with your
smartphone or tablet for a 123BIM
interactive Virtual Tour.

No Compromise Press Release | North Washington Street Bridge QR

Or click on this URL:
https://vtourdev.123bim.com/AAEH

Story Board Video

Watch the video produced by RDV Systems for MassDOT

Click to play video

Contact Us Today!

Western US
Larry Mohr

Southern US
James Brown

Northeast US
Kevin Stewart

Florida
Gary Rackliff

RDV Systems – Laser Focused on Safety